This E2E test plan validates that D365 F&O is configured correctly and that all NordHav business processes can be executed end-to-end. Each scenario is traced from its business process start through to financial impact.
Environment
UAT environment
Audience
Implementation team
Timeline
T-12 to T-8 weeks
Environment
UAT environment
Audience
NordHav key users
Timeline
T-8 to T-4 weeks
Environment
UAT environment
Audience
IT + implementation team
Timeline
T-6 weeks
Environment
Production (smoke test)
Audience
NordHav Finance Director
Timeline
Go-live day
Owner: Head of Procurement
Target: T-4 weeks
Owner: CFO + Head of Sales
Target: T-4 weeks
Owner: Head of Processing
Target: T-4 weeks
Owner: CFO + Finance Controller
Target: T-4 weeks
Owner: HR Director
Target: T-4 weeks
Owner: Technical Director
Target: T-3 weeks
Owner: CFO + Finance Controller
Target: T-3 weeks
Owner: Quality Director
Target: T-3 weeks
| Test Scenario | Test Data Required |
|---|---|
| E2E-001 Procure to Pay | Test vendor EWOS feed order; test inventory stock in SEA-01-FEED |
| E2E-002 Harvest to Invoice | Test production order for SAL-FG-001; test customer NorgesGruppen |
| E2E-003 VAP Production | Test VAP production; test export customer Ahold Delhaize |
| E2E-004 CAPEX Lifecycle | Test CAPEX project with 2 vendor invoices |
| E2E-005 HR Leave | Test employee with current leave balance |
| E2E-006 Maintenance WO | Test asset at SEA-01; test spare part inventory item |
| E2E-007 Month-End Close | Full month of transaction activity (simulated or from SIT) |
| E2E-008 Quality NCR | Test production batch; quality test configuration complete |